| FHWA > Asset Management > Case Studies > PMS: The Washington State Experience > Introduction |
Transportation Asset Management Case Studies
|
| Implementation of the pavement management system by WSDOT has helped the State to improve its pavement condition significantly. |
The WSPMS uses pavement structural condition (PSC) as a trigger value to identify candidate pavement projects, as described in the following paragraphs:
Overall pavement distress is termed pavement structural condition (PSC) and is calculated separately for flexible and rigid pavements. The PSC has an upper limit of 100 (no distress) and a lower limit of zero (extensive distress). WSDOT attempts to program rehabilitation for pavement segments when they are projected to reach a PSC of 50.6
WSDOT has given careful consideration to the formulation and interpretation of the PSC itself, and the value of the PSC threshold, in terms of how pavement rehabilitation projects in Washington should be programmed. Cost analyses [lowest life-cycle cost] performed by WSDOT show that unit costs of rehabilitation increase by a factor of three to four for [hot-mix asphalt (HMA)] projects programmed at a PSC of zero compared to projects programmed at a PSC of 40 to 60.7
Initial development of threshold values for lowest-life-cycle cost approach was based only on agency costs and did not include user costs…. Threshold values for rutting to address safety and roughness to address user cost were subsequently implemented in identifying [candidate] projects.8
WSDOT employs the following process to develop a prioritized list of projects.
Using the pavement condition and performance curves, the WSPMS can forecast the expected [optimum] time to the next rehabilitation for each pavement section. Each candidate project is assigned to a priority group according to its predicted "due date." 9
For example, if a pavement section is expected to reach a PSC equal to 50 in 2008, then the pavement section is considered "due" for rehabilitation in 2008.
Priority groups are defined by individual year only for those six years that are encompassed by the investment program. These priority groups, taken collectively, form the priority listing of pavement preservation needs. The priority listing is a useful tool for the central [headquarter] office, program managers and the regions in developing the biennial preservation program. However, the list is supplemented by [review of the digital images collected as part of annual pavement condition data collection and] additional site visits to verify accuracy, assess causes of defects and determine abilities of the maintenance program to apply preventative or short term remedial treatments before a biennial program is developed.10
It should be noted that WSDOT takes into consideration the importance of the candidate projects on high-volume routes while preparing the priority list.
WSDOT attempts to rehabilitate high volume routes (interstate and principal arterial routes) when they are "due" and prevents them from reaching the "past due" category. Also, as part of the biennium rehabilitation projects selection process, "past due" projects may be included if increased user costs on high-volume routes justify their selection.11
Clearly, the focus of the WSDOT pavement management program is on pavement preservation. As mentioned previously, 27 percent of the entire system receives a bituminous surface treatment on a 6-to 8-year cycle. WSDOT applies this type of treatment to low-volume roads with an annual average daily traffic less than 2,000. Typically, 100 percent of chip seal projects that are due are programmed first. The remaining funds address rehabilitation projects (nearly 90 percent of rehabilitation projects are 50-mm [2-in.] overlay projects) with PSC values between 40 and 60, and if any funds are left, remaining past due projects will be programmed.
| The pavement management system can forecast the optimal time for the next rehabilitation for each pavement section. |
Implementation of the pavement management system by WSDOT has helped the State to improve its pavement condition significantly. For all route classifications (Interstate, Principal Arterial, Minor Arterial, and Major Collector), the overall PSC scores from 1971 to 2006 are shown in Figure 2. As stated in Washington State Highway Pavements: Trends, Conditions, and Strategic Plan, May 1999,12 "it is notable how this condition measure has improved since 1971-noteworthy is the reduction of those pavements being in the very poor category from about 20 percent of the total lane-miles in the early 1970's down to about one percent in 1994 and later."
In 1971, almost 50 percent of the State's pavements were in poor and very poor condition. Today, a little more than 10 percent of the roads are in poor and very poor condition.
Figure 2. Trends in Washington State pavement structural condition, 1969–2006 (statewide, all pavements). Data source: Washington State Department of Transportation Materials Lab.

| << Previous | Contents | Next >> |
Nastaran Saadatmand
Office of Asset Management
202-366-1337
E-mail Nastaran